On the morning of May 17, the representative of Qinghai Huangdian Gonghe Photovoltaic Power Generation Co., Ltd. sent two pennants with the words "Excellent Photovoltaic Power Station Supporting System Supplier" and "Win-Win with virtue, Responsibility, Quality, Excellence and Demeanor" to the delivery personnel of our company , in recognition of Versol's excellent performance in the power supply configuration project of the UHV transmission base in Hainan Prefecture, Qinghai Province.
The power supply configuration project of UHV transmission base in Hainan Prefecture, Qinghai Province Talatan Project in Hainan Province is located in Talatan, Gonghe County, Hainan Tibetan Autonomous Prefecture, Qinghai Province.The project site area is located in the photoelectric park of the 10-million-kilowatt new energy base (one district and two parks) in Hainan Prefecture, about 43km away from Gonghe County. The total installed capacity of the three tenders is 2200W, covering an area of about 17.616km².
Versolsolar undertook the task of supplying 400MW brackets in this project. At the beginning of the project, our technicians considered the characteristics of strong wind and sand, special terrain environment, low temperature for a long time, and complicated construction methods, and comprehensively considered the quality of the power station, the actual construction difficulties and economic benefits, then decided to use V-In tracking system to ensure the construction progress and power station benefits.
After experiencing many difficulties such as shortage of raw materials and workers, poor logistics and other difficulties brought about by the Covid-19, we transported the brackets to the project site on time. The project is large, the land is wide, and the tasks are heavy. In the process, it is necessary to cooperate with the owner and the progress of the other organizations because a lot of detailed communication and planning arrangements are required. Our delivery and technical personnel are stationed on site to support the whole process to ensure the first response Customer on-site needs. It is this meticulousness and devotion that makes us and our customers become good partners and friends. The Versol staff on site orderly commanded dispatching, counting, handling, and commanded the installation of brackets, etc., coordinated the progress of all parties, and contributed to the construction of the power station.
Today, the project has been successfully connected to the grid, and Versol's performance in this project has been affirmed and appreciated by customers. The completed power station is vast and stunning, and the pennant we received is dazzling. This is encouragement, but also responsibility. It is to remind us to use higher standards to demand ourselves and serve customers. Versol will always adhere to the service spirit of "customer first, fulfillment of contract firstly". In the spirit of pragmatism and innovation, persistence and hard work, we concentrate on making efforts, forge ahead, and bring better products and services to our customers , and continue to provide our customers with more competitive power generation gains and power resource operation capabilities.